CM 1: CM Planning  

  KM1 - KM-Planung

Contents  
  • Product Flow
  • Handling
  • Explanation
  • Roles
  •  
  • Sub-activities
  • Tools Requirements
  • External Norms
  • Links to the V-Model Mailinglist
  • Product Flow

    From Product to Methods Tool Req. Ext. Norms
    Activity State Chapter Title Activity State
    PM1 accepted All Project Manual - -      
    PM1 being proc. All Project Plan - -    
    - - All CM Plan CM2 ,
    CM3 ,
    CM4
    submitted    

    + "Chapter" are extra columns from the original printed version of GD 250

    Further Results:
    . Product library
    . Tools

    Handling

    Figure 6.3

    Figure 6.3: CM1 - CM Planning

    The CM planning is the first CM-related activity. It is to define the organizational framework by means of the CM Plan. Furthermore, resources like the product library and the corresponding tools have to be made available.

    Explanation

    All products are-as far as it is practical and possible-collected and maintained in the product library. Products that are administered by the CM refer to documents and SW and HW items.

    The product library is an instrument of the SD and used to administer stored DP information for the entire project. The identification system established in the CM Plan must be adhered to when identifying and referencing all products. Contrary to the stored DP documentation, the physical storage of the HW items is typically realized outside of the SD product library. Therefore, the V-Model does not include regulations for the physical administration of HW items.

    Roles

    Role Participation
    CM Administrator responsible (CM1.2)
    CM Manager advising (CM1.1)
    CM Representative advising (CM1.2
    responsible (CM1.1)
    Project Leader cooperating (CM1.1)

    Sub-activities

    CM1.1 - Generation the CM Plan,
    CM1.2 - Setting up CM

    Tools Requirements

    Being defined

    External Norms

    Being defined

    Links to the V-Model Mailinglist

    Mail 0503 - KM- und QS-Initialisierung (503)