Previous Next V-Model Official Homepage by IABG  
Header  
CM 1.1: Generation of CM Plan  

  KM1.1 - KM-Plan erstellen

Contents  
  • Product Flow
  • Handling
  • Explanation
  • Roles
  •  
  • Tools Requirements
  • External Norms
  • Links to the V-Model Mailinglist
  • Product Flow

    From Product to Methods Tool Req. Ext. Norms
    Activity State Chapter Title Activity State
    PM1 accepted All Project Manual - -      
    PM1 accepted All Project Plan - -    
    - - All CM Plan CM1.2 ,
    CM2
    CM3
    CM4.4
    submitted    

    + "Chapter" are extra columns from the original printed version of GD 250

    Handling

    The sections 2. Introduction of the Configuration Management, 3. Change Management and 4. Data Backup and Archiving in the CM Plan have to be completed within the scope of the CM1 - CM Planning.

    With regard to the CM introduction strategy it must be stated, among other things,

    Deviations from the V-Model rules with regard to the product states are only allowed in as far as a mapping of the states and state transitions as defined in the V-Model to project-specific regulations is possible. As a consequence, states can only be refined and not combined or even deleted.

    Explanation

    For small projects it is possible to maintain the CM Plan together with the PM planning documents Project Plan and Project Manual.

    Roles

    Role Participation
    Project Leader cooperating
    CM Manager advising
    CM Representative responsible

    Tools Requirements

    Being defined

    External Norms

    Being defined

    Links to the V-Model Mailinglist

    Mail 0322 - KM 1.1: KM-Plan erstellen (322)

    Previous Next GDPA Online Last Updated 01.Jan.2002 Updated by Webmaster Last Revised 01.Jan.2002 Revised by Webmaster