CM 3.2: Decision about Change Procedures and Initiation of Change  

  KM3.2 - Änderungsvorgehen entscheiden und Änderung einleiten

Contents  
  • Product Flow
  • Handling
  • Roles
  •  
  • Tools Requirements
  • External Norms
  • Product Flow

    From Product to Methods Tool Req. Ext. Norms
    Activity State Chapter Title Activity State
    CM1 accepted All CM Plan - -      
    External (1) - All Change Request/Problem Report - -    
    CM3.1 - All Change Proposal - -    
    - - All Change Order (2) CM3.3
    to submodel in question
    -    
    - - All Protocol CM4.5,
    External (1)
    -    
    CM3.1 - All Change Status List CM3.3,
    CM4.5
    -    

    + "Chapter" are extra columns from the original printed version of GD 250

    Handling

    A decision must be made about the change procedure, and the corresponding measures have to be initiated.

    When coming to a decision about the change and when initiating the change, the following roles will participate:

    If none of the proposed solutions is accepted a report has to be written or else a proposal for a solution is selected which will be the basis for a Change Order. This activity is to be coordinated with the PM activity PM4 - Detailed Planning and PM7 - Risk Management

    According to the contractual provisions, the customer is to be involved, if necessary.

    When realizing the changes, the regulations of the V-Model have to be adhered to.

    Roles

    Role Participation
    Project Leader responsible
    CM Representative cooperating
    CM Administrator cooperating

    Tools Requirements

    Being defined

    External Norms

    Being defined


    Notes:

    (1) project member, customer, user

    (2) in the case of a positive decision