8.3.2 Assessment Plan (AsPl)  

  Prüfplan

Contents  
  • Introduction
  • Document Index
  • Document Structure
  • Links to the V-Model Mailinglist
  • Introduction

    The Assessment Plan defines the objects to be assessed as well as the tasks and responsibilities of the assessments, the planning schedule, and the resources required for the realization. The Assessment Plan determines the state in which products and activities have to be assessed, also when, by whom, and by what means they have to be assessed.

    Either an Assessment Plan binding for all assessments and oriented on the actual project situation is generated or, for practical reasons, the Assessment Plans are separated physically into several plans comprising subsets of the assessments. Such a partitioning might be realized on the basis of subprojects or reference products (System, Segment, SW Unit/HW Unit).


    Document Index

    1. General Information
    2. Objects to be Assessed and Qualification Requirements
    3. Tasks and Responsibilities
    4. Time Schedule
    5. Resources
          5.1. Assessment Environment
          5.2. Further Resources

    Document Structure

    1. General Information

    See schema 1. General Information.

    2. Objects to be Assessed and Qualification Requirements

    The objects to be assessed in an assessment by QA are stated in their concrete instantiation, and the corresponding quality requirements will be described. The assessed objects are: Furthermore, based on strict quality requirements it might also be necessary to set up assessments for the following objects to be assessed: The identification of the objects to be assessed (System, Segments, SW Units/HW Units, SW Components, Databases, and documents) is performed according to the conventions set up in the CM Plan.

    The content of this structural item is not redundant to the item Products to be Assessed of the QA Plan. In that plan the products are identified based on their neutral names, e. g. SW Architecture; in this case, however, they have to be made concrete for the project (e. g. SW Design (Module) for the SW Module "logarithm calculation").

    3. Tasks and Responsibilities

    For each organizational unit involved in the assessment (mentioned in the QA Plan) the responsibility with regard to the assessment will be briefly described. It is thereby differentiated between executing, cooperating, advising, or controlling participation. Furthermore, the individual assessments are allocated to persons who are mentioned by name.

    In the cases of assessing the products SW Unit or HW Unit, Segment and System, this item is closely connected with the corresponding structural item of the product Integration Plan.

    4. Time Schedule

    The actual SW lifecycle with its baselines and the marginal conditions for the development determine the chronological order of the assessments. This chapter has to include the dates for the preparation and execution of the above mentioned objects to be assessed and for the phase reviews' preparations.

    In the cases of assessing the products SW Unit or HW Unit, Segment and System, this item is closely connected with the corresponding structural item of the product Integration Plan.

    5. Resources

    5. 1. Assessment Environment

    This describes the assessment environment required for the assessment. Should an assessment environment already exist, it must be uniquely identified with its HW items (devices, analyzers, monitors, testrigs, etc.) and SW items (system software, firmware, simulators, test data generators, test drivers, stubs, etc.); otherwise the requirements for this environment have to be defined.

    5. 2. Further Resources

    Resources required in addition for individual assessments (IT resources, on-the-job infrastructure, means of work) must be listed, together with individual details as to when and to what extent the resources have to be available.

    Links to the V-Model Mailinglist

    Mail 0364 - Re: Pruefplan - Qualifikationserfordernisse
    Mail 0362 - Pruefplan - Qualifikationserfordernisse
    Mail 0286 - Re: Organisationseinheiten im QS-Plan / Pruefplan (286)
    Mail 0278 - Re: Organisationseinheiten im QS-Plan / Pruefplan (278)
    Mail 0273 - Organisationseinheiten im QS-Plan / Pruefplan (273)
    Mail 0208 - Re: Tailoring / QS (208)
    Mail 0206 - Tailoring / QS (206)
    Mail 0204 - Re: Produktzustand des Pruefplans (204)
    Mail 0203 - Produktzustand des Pruefplans (203)

    Previous Next GDPA Online Last Updated 01.Jan.2002 Updated by Webmaster Last Revised 01.Jan.2002 Revised by Webmaster