Previous Next V-Model Official Homepage by IABG  
Header  
PM 1.4: Toolset Management  

  PM1.4 - Toolset-Management durchführen

Contents  
  • Product Flow
  • Handling
  • Recommendation
  • Explanation
  •  
  • Roles
  • Tools Requirements
  • External Norms
  • Links to the V-Model Mailinglist
  • Product Flow

    From Product to Methods Tool Req. Ext. Norms
    Activity State Chapter Title Activity State
    PM1.2 ,
    PM1.3
    being proc. All Project Manual - -     /ISO IEC 12207/

    Supply Proc.:
    Planning,

    Devlp. Proc.:
    Proc. Implement.,

    Infraest. Proc.:
    Proc. Implem.

    - - 6 Project Manual.
    Selection of Methods and Tools
    PM1.5
    PM2
    PM3
    PM4
    PM8
    PM10
    PM11
    PM12
    CM1
    CM4.7
    QA1
    submitted    
    - - 8 Project Manual.
    Standards and Regulations
       

    + "Chapter" are extra columns from the original printed version of GD 250

    Further Results:
    Selection of development environment/assessment environment

    Handling

    The goal of this activity is the selection of tools for the realization of the project.

    The methods and tools as well as the standards and regulations must be defined for all submodels. The methods and tools must be bindingly allocated to the activities and products of the project-specific V-Model.

    The selection of methods and tools is realized on the basis of standards or recommended tools. Provided that the adherence to certain standards is mandatory-like GD 251 and GD 252 for the German MoD field-the standard conformity for the specifications must be proven.

    The participants (customer, contractor, user) must agree about which methods and which tools are to be established.

    Apart from the selection of methods and tools for the development environment and the definition of standards and regulations, this activity includes the preselection of the target computer equipment and the tools related to the target computers.

    Special requirements with regard to the development environment and tools related to the target computers (e. g. cross compilers) resulting from the actual quality requirements for the software to be developed are generated and established in submodel SD. This may also result in the update of the specifications in activity PM1.4 - Toolset Management.

    If necessary, it will be determined by special proof tests whether the selected tools are suitable.

    The IT measures realized by security functions or other concepts require a trustworthiness that meets the reliability requirements. This is also determined by the quality of its implementation (e. g. E-level). Depending on this, however, a development environment must be selected that meets the requirements.

    If necessary, minimum requirements have to be met with regard to methods and tools.

    Based on IT security reasons, special requirements may be set up in order to differentiate between various users and roles and to guarantee their accountability within the development environment.

    This may help

    Recommendation

    With regard to the later SWMM, long-term technology planning is required; it must meet the following criteria:

    Explanation

    The project criteria defined within the scope of activity PM1.2 - Definition of Project Criteria and Development Strategy may have anticipated a more final selection of methods and tools.

    Further relevant criteria are also reliability and robustness of a tool, distribution and references, compatibility, adaptability, maintainability, flexibility, network readiness, support, use by the staff member in charge of the application, other contractors, customer and subcontractors.

    The project management has to ensure of adequate application support. This requires:

    Roles

    Role Participation
    Project Leader responsible
    Project Administrator cooperating
    IT Representative advising
    SD Supervisor cooperating

    Tools Requirements

    Being defined

    External Norms

    Norm Process Chapter Obs.
    /ISO IEC 12207/ Supply Process Planning (s. Part 3 - ISO 3.2.1)
    Development Process Process Implementation (s. Part 3 - ISO 3.2.1)
    Infraestructure Process Process Implementation (s. Part 3 - ISO 3.2.3)

    Links to the V-Model Mailinglist

    Mail 0629 - PM 1.4 - Wer akzeptiert das Projekthandbuch? (629)
    Mail 0618 - Re: Erstellen von Programmierrichtlinie (618)

    Previous Next This page online  •  GDPA Online  •  Last Updated 05.Feb.2003 by C. Freericks