PM 9: Information Service/Reporting  

  PM9 - Informationsdienst/Berichtswesen

Contents  
  • Product Flow
  • Handling
  • Recommendation
  •  
  • Roles
  • Tools Requirements
  • External Norms
  • Product Flow

    From Product to Methods Tool Req. Ext. Norms
    Activity State Chapter Title Activity State
    CM4 being proc. Existing Project History - -     /ISO IEC 12207/

    Supply Proc.:
    Exec. and Control,

    Mngmt. Proc.:
    Exec. and Control

    QA5 - All Report Documents:
    Protocol ,
    Progress Report
    Final Project Report
    Case Report
    Memo
    Internal Message
    Invitation
    CM4
    External (1)
    -    

    + "Chapter" are extra columns from the original printed version of GD 250

    Handling

    The goal of this activity is to make the information status required for the realization of the tasks available. This has to be done periodically or according to the individual information requirements and the individual requirements offered.

    Within the scope of the information service both customer and project members are kept informed about the project. The project management thus acts as the information interface of the project and keeps in touch with staff members, customer, users and possibly the subcontractors.

    The information service includes:

    Depending on the development course and the contracts, the reports defined in the Project Plan have to be generated within the scope of reporting.

    Recommendation

    A presentation of the achieved results should not only take place at the time the project has been completed, but also after decisive activities have been completed, i. e. at defined milestones in order to include users and customer continuously into the project early enough.

    The project management can realize this activity itself or it might delegate it to those in charge of SD or QA activities.

    Roles

    Role Participation
    Project Leader responsible
    Project Administrator cooperating

    Tools Requirements

    Being defined

    External Norms

    Norm Process Chapter Obs.
    /ISO IEC 12207/ Supply Process Execution and Control (s. Part 3 - ISO 3.2.1)
    Management Process Execution and Control (s. Part 3 - ISO 3.2.3)


    Note:

    (1) distributor according to Project Plan

    Previous Next GDPA Online Last Updated 01.Jan.2002 Updated by Webmaster Last Revised 01.Jan.2002 Revised by Webmaster