RE 6: SW Integration  

  RE6 - SW-Integration

Contents  
  • Product Flow
  • Handling
  • Sub-activities
  • Product Flow

    From Product to
    Activity State Chapter Title Activity State
    RE3 accepted All Integration Plan - -
    RE5 accepted All Implementation Document: SW Module - -
    All SW Module
    All Implementation Document: Database
    All Database
    - - All Implementation Document: SW Unit RE7
    External (1)
    submitted
    - - All SW Unit RE7 submitted

    Handling

    Figure RE.6
    (start daVinci Graph Visualization Tool v2.0)

    Figure RE 6: SW Integration

    This activity integrates the SW Modules and Databases into a SW Unit. During the integration, the regulations set up in the Integration Plan are applied.

    Sub-activities

    RE 6.1: Integration into SW Unit
    RE 6.2: Self-Assessment of SW Unit