    From Product to
    Activity State Chapter Title Activity State
    RE7.3 accepted All Operational Information:
    User Manual
    Diagnosis Manual
    Operator Manual
    Other Application Information
    - -
    RE8.3 accepted All System (installed) - -
    - - All System (installable and in operation) External (1) submitted

    Handling

    It is the objective of the activity to renew the initial operation of the system and to prepare it for the acceptance test as well as for the smooth transition into cooperation with the updated IT system.

    In order to support the renewed initial operation, the following measures have to be taken:

    All data volumes required in the updated System must be transferred from the old System. The required initial data collection must be realized.

    For a certain period of time, it might be necessary that the old operating procedures are used to guarantee a smooth operation, or the old System must be used in parallel to the new System.

    The old System must be removed (e. g. termination of licenses, deletion of data volumes, recycling old hardware systems) according to the legal requirements.