Previous Next V-Model Official Homepage by IABG  
Header  
SD 4.3-SW: Specification of SW Integration  

  SD4.3-SW - SW-Integration spezifizieren

Contents  
  • Product Flow
  • Handling
  • Roles
  •  
  • Methods
  • Tools Requirements
  • External Norms
  • Product Flow

    From Product to Methods Tool Req. Ext. Norms
    Activity State Chapter Title Activity State
    SD4.2-SW accepted All Interface Description - -     /ISO IEC 12207/

    Devlp. Proc.:
    SW Integr.

    SD4.1-SW accepted All Software Architecture - -    
    SD4.1-SW being proc. Existing Operational Information:
    User Manual
    Diagnosis Manual
    Operator Manual
    Other Application Information
    SD5-SW being proc.    
    SD2 being proc. Existing Integration Plan SD7-SW
    SD8
    QA2
    submitted BAR (1)
    DTAB (2)
    NPT (1)
    SPM04

    + "Chapter" are extra columns from the original printed version of GD 250

    Handling

    For the Integration Plan, regulations and procedures for the assembly of the SW Unit made up of SW SW Components, and the SW Components in turn made up of SW Modules and Databases, must be regulated from a technical point of view. The Integration Plan must be generated with regard to deadlines, resources, tools, personnel, Off-the-shelf-products, interfaces, and other similar influences, and in cooperation with the project management. Configuration of the SW Unit and all information pertinent for the integration activity have to be established in the Integration Plan; information for the integration test must be derived and documented.

    The tasks in connection with the Integration Plan also yield further details for the Operational Information. The Information for the Operator Manual and the Information for the Diagnosis Manual have to be updated; in particular the information with regard to the availability of the facility and the environment components as well as the start and end of operation will be completed. In Other Application Information all those particularities must be documented that refer to installation and configuration. The present Interface Description yields clues for the refinement of the Information for the User Manual.

    Roles

    Role Participation
    SW Developer responsible
    Technical Author cooperating

    Methods

    Product Methods Allocation Use
    Chapter 4.1
    Integration Plan.
    Integration Network Plan
    BAR - Bar Plan (1) Generate
    NPT - Network Planning Technique (1) Generate
    Chapter 5.2
    Integration Plan.
    Integration Instructions
    DTAB - Decision Table Technique (2) Generate

    Tools Requirements

    Product Functional Tools Requirements
    Integration Plan.Organization of the Integration SPM04 - Supporting Planning of the Project Realization

    External Norms

    Norm Process Chapter Obs.
    /ISO IEC 12207/ Development Process Software Integration (s. Part 3 - ISO 3.2.1)


    Notes:

    (1) Method NPT is to be applied if very complex call and integration relations among the functional units have to be taken into consideration which in particular break through the hierarchical top-down or botteom-down relations several times; otherwise method BAR is to be applied.

    (2) Method DTAB is to be applied for the description of complex facts and circumstances.

    Previous Next GDPA Online Last Updated 01.Jan.2002 Updated by Webmaster Last Revised 01.Jan.2002 Revised by Webmaster