Previous Next V-Model Official Homepage by IABG  
Header  
SD 7.3-SW: Integration into SW Unit  

  SE7.3-SW - Zur SW-Einheit integrieren

Contents  
  • Product Flow
  • Handling
  • Roles
  •  
  • Tools Requirements
  • External Norms
  • Product Flow

    From Product to Methods Tool Req. Ext. Norms
    Activity State Chapter Title Activity State
    SD6-SW accepted All Implementation Document: SW Module - -      
    - SW Modules    
    All Implementation Document: Database    
    - Database    
    SD7.2-SW accepted All Implementation Document: SW Component - -    
    - SW Component - -    
    SD4-SW accepted All Integration Plan - -    
    - - All Implementation Document: SW Unit SD7.4-SW being proc.    
    - - - SW Unit   SSD16

    + "Chapter" are extra columns from the original printed version of GD 250

    Handling

    In this activity, SW Modules, Databases and SW Components are integrated into the SW Unit. This is realized just as activity SD7.1 - Integration into SW Component whereby different procedures may be used (defined in the Integration Plan).

    The resulting SW Unit must not contain any dummies.

    Roles

    Role Participation
    SW Developer responsible

    Tools Requirements

    Product Functional Tools Requirements
    SW Unit SSD16 - Linking

    External Norms

    Being defined