Previous Next V-Model Official Homepage by IABG  
Header  
SD 8.3: Product Supply  

  SE8.3 - Produkt bereitstellen

Contents  
  • Product Flow
  • Handling
  • Roles
  •  
  • Tools Requirements
  • External Norms
  • Product Flow

    From Product to Methods Tool Req. Ext. Norms
    Activity State Chapter Title Activity State
    SD5-SW being proc. Existing Operational Information:
    User Manual
    Diagnosis Manual
    Operator Manual
    Other Application Information
    SD9 submitted      
    SD8.2 accepted All System - -    
    - - All System (installable) SD9 submitted    

    + "Chapter" are extra columns from the original printed version of GD 250

    Handling

    To support the introduction of the System, the following measures have to be realized:

    * Completion of the Operational Information

    The Information for the Operator Manual, the Information for the User Manual, the Information for the Diagnosis Manual and Other Application Information for the System that have been generated during development have to be updated and completed.

    * Provisioning an Installable System

    The System must be made available in an installable form (e. g. on the appropriate data media like floppy disks, CD-ROM).

    Roles

    Role Participation
    System Designer responsible
    SW Developer cooperating
    HW Developer cooperating
    Technical Author cooperating
    System Administrator cooperating

    Tools Requirements

    Being defined

    External Norms

    Being defined

    Previous Next GDPA Online Last Updated 01.Jan.2002 Updated by Webmaster Last Revised 01.Jan.2002 Revised by Webmaster